Estimation from a development-to-test ratio
QuizEasy-MediumAsked in: Infosys, TCS, Wipro
On similar past projects, development effort and test effort were in the ratio 5 : 2. The new project needs about 250 person-days of development (one person-day is one person working for one day). Using this ratio, how much test effort do you estimate?
- 100 person-days
- 50 person-days
- 125 person-days
- 625 person-days