Three-point estimation: calculate the estimate

QuizMediumAsked in: Infosys, TCS, Wipro

For testing a new module, the team gives three estimates: optimistic 4 days, most likely 6 days, pessimistic 14 days. Using three-point estimation, which weights the most likely value four times, E = (optimistic + 4 x most likely + pessimistic) / 6, what is the estimate?

  • 7 days
  • 6 days
  • 8 days
  • 24 days